Expanding a working laundry is also a continuity project. The key question is how existing work will be delivered while installation and commissioning take place, not simply where the new machines will stand.
List daily delivery obligations and the linen turnaround they require. Confirm available stock and any agreed flexibility in collection times. Treat backup arrangements as commitments only after they are confirmed. A delivery date for equipment is not the same as a date for dependable production.
New equipment may rely on existing utilities. Have the responsible specialists assess simultaneous demand and identify which connection tasks require shutdowns. Preserve access for servicing existing machines and moving linen. A layout with more installed capacity can still be harder to operate if carts and technicians cannot move through it.
Separate preparation, positioning, connection, commissioning, trial operation and production transfer. Define what completion means at each stage and what happens if a check fails. Move work progressively after the agreed trial conditions are met, rather than removing every existing option before the replacement is ready.
Compare delivery reliability, queue locations, handling effort and interruptions with the pre-project baseline. If the expected capacity is not available, investigate the remaining constraint before adding further equipment. The purpose of expansion is dependable delivered work, which is a more meaningful outcome than installed capacity alone.